Hello
Created two sprints with multiple tasks e.g Sprint1 and Sprint2 thy work parallel and independent on same time.When i click on active sprints it shows me only Sprint1 in backlog both sprints are visible
Hello @hamida Khanam , Go to the settings and navigate to the products and then go to Jira Software Configuration and enable parallel sprints.
Hope this helps you :)