Hi,
I am using JIRA 6.1.1 and i am now settin up our Agile module,
I am now looking into estimate time feature - and i couldent put it on the create issue window
I have added the time tracking filed and log work - but i dont understand where people should put there time estiation
Thanks
Naama
Hi ,
Thanks for your comments - i have found the issue -
from some reason time tracking was set on 'hide' mode for all my screens
Thanks
Naama
Time tracking field should display both estimated and time remaining on the screen. There is no separate field for original estimate. Is it not working when you add time tracking field on to Create screen?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
it didnt work.. i have added the log work filed and the time tracking field -
but all i can see is the remaining estmate part
Can you please advise?
Thanks
Naama
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Where do you see the "remaining estimate"? If you're seeing that, you should be seeing three lines - original, remaining and logged work. If you're seeing only one, I'm not sure what you're looking at.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.