My team completed 34 story points of work in sprint 2. For whatever reason, when closing my sprint, 3 of the completed stories (445, 459, and 455) were moved to Sprint 3 and are thus showing up incorrectly in the release burndown report which will throw off the forecast.
Any ideas on how to fix this?
Screenshots:
I found this:
In the 'Completed Issues' table, an issue is grouped into a sprint if its completion date falls after the start date of the sprint and before the start date of the next sprint, regardless of whether it was assigned to the sprint during planning.
For example, consider the following sample data:
Sprint 1 — starts on July 1 and ends on July 14
Sprint 2 — starts on July 17 and ends on July 30
Say issue 'ABC-123' was assigned to Sprint 1 during planning, but was not completed until July 18. In the 'Completed Issues' table, ABC-123 would be grouped under Sprint 2, rather than Sprint 1. This is a more accurate reflection of what happened during the release and helps maintain the integrity of the report data.
Here's more details: Below you can see that the stories were completed in sprint 2, why are they showing up in sprint 3 on the release burndown?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.