It would be very useful to know in a burn-down where the time is being spent by each person (helps a lot with the sprint retorspective). Any way of getting at that info? Thanks!
Hi Vadim,
Perhaps is not possible in GH, but you can use JIRA Timesheet report instead which can generate the time spent for each issue, you can export it to Excel which can help you better to generate a better representative charts for the data (something like burndown chart).
Hope it helps !
Omar
Thanks, Omar! We're using hosted JIRA - I'm not sure Tiemsheet is available there yet.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Vadim, indeed is included in OnDemand :) . You can access it under Reports from the 'Project' view.