How do I make the tick beside a subtask go away

Q_M
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 2, 2020

I have created a few sub-tasks under a story. Once I mark a sub-task as done, a tick would appear under Sub-tasks section of a story. However, if I want to change the status of the sub-task back to "to do", the tick still persists. Is there a away to make it go away?

 

Thank you!Capture.PNG

1 answer

0 votes
Maxine Kröll
Community Champion
April 3, 2020

Good morning Q_M, 

 

please check the resolution field of the sub-task with the tick. You can find the resolution field below the status if you go into the detail view of your issue. 

2020-04-03_09h08_02.png

If the resolution does not show "unresolved", that could be the reason why the tick is still there. 
If an issue has a resolution set, Jira recognizes the issue as resolved. If the resolution is "unresolved", it's unresolved for Jira as well. There's not native connection to your "Done" status. 

Please check if this seems to be your problem and if yes I am happy to describe how you need to change your workflow if you need help with that.

Kind regards

Maxine