How do i define a starting date for a task or an issue?

Panshul Gupta January 28, 2013

How do I define a starting date for a task or an issue?

I can define a due date for a task or an issue, but I do not see any option to define a starting date for the issue or task.

Please suggest a way to assign a starting date for a issue or task as I would like to define a date when a member should start working on a pre defined task, in cases when the task has a dependancy which needs some pre known amount of time to complete.

Is there a way or should I post a feature request for it? and wait for next release?

Thnx.

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 28, 2013

That's not how most development projects work in Agile (which is roughly what Jira is aimed at), so it's not a system function, and probably never will be.

However, it's a doddle to implement - add a custom field of "start date".

Panshul Gupta January 29, 2013

thnx, that really helped