During the sprint planning the SM asks the team members their capacity in hrs/days in the sprint so the team can understand how much a team member can take. If the sprint is two weeks a member can be the first week on vacation therefore his capacity is 50% or 40 hrs in that sprint.
I also use MS TFS which has this feature to help the team understand how much they can plan for in the current sprint. It quantifies it in hours or days.
Hi @Liviu Meister -- Welcome to the Atlassian Community!
I do not believe there is a built-in feature for Classic or Next-Gen projects in JIRA Cloud. There are probably marketplace add-ons which you could purchase.
There are several suggestions to add capacity management to JIRA, which you can review and vote for:
Best regards,
Bill
Thanks Bill. I will investigate your proposals.