I have a sprint that has the following dates:
Start date: 20/May/19 11:03 AM
End date: 20/May/19 11:59 PM
When I start the sprint, it says that the sprint has 0 working days even though the dates encompass 1 working day. Can anyone offer a definitive explanation?
Thanks Mirek
So how i can set these values that it shows 1 working days
Start date: 20/May/19 11:03 AM
End date: 20/May/19 11:59 PM
Change the End Date to be more than 24h from your current time and make sure that next day is a workday not weekend. Then it should switch to 1 remaining day..
PS. Sometimes you need to refresh your browser.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI @Jawad Haider ,
From what I know Jira calculates this days left in 24 hour increments but also respecting timezones and working days that are defined on a board. And this is not calculating days from Start to End dates but from current time to end date.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.