How does Jira Agile calculate the days in a sprint?

Jawad Haider May 20, 2019

I have a sprint that has the following dates:

    Start date: 20/May/19 11:03 AM

    End date: 20/May/19 11:59 PM

When I start the sprint, it says that the sprint has 0 working days even though the dates encompass 1 working day. Can anyone offer a definitive explanation?

 

 

 

2 answers

0 votes
Jawad Haider May 20, 2019

Thanks Mirek

 

So how i can set these values that it shows 1 working days

 

Start date: 20/May/19 11:03 AM

    End date: 20/May/19 11:59 PM

Mirek
Community Champion
May 21, 2019

Change the End Date to be more than 24h from your current time and make sure that next day is a workday not weekend. Then it should switch to 1 remaining day..

PS. Sometimes you need to refresh your browser.

0 votes
Mirek
Community Champion
May 20, 2019

HI @Jawad Haider ,

From what I know Jira calculates this days left in 24 hour increments but also respecting timezones and working days that are defined on a board. And this is not calculating days from Start to End dates but from current time to end date.

Suggest an answer

Log in or Sign up to answer