How is Original estimate set to show weeks and days instead of hours ?
Currently I set it to for example 7d and get 52,5h :( that is not what I want to show.
Hi @Ville Manner ,
you can change this setting in Issues -> Issue features -> Time tracking.
The URL is like this : https://mycompany.atlassian.net/secure/admin/TimeTrackingAdmin.jspa
Here you can set the display to hours, days, or mixed :
Let me know if this helps,
--Alexis