Hi,

I created a JIRA plan but I would like to see in the timeline at the top the different sprints so I can see which stories belong to which sprint after adding them to the plan and defining the start and end date. Relases can be added to the timeline but how to add the sprints?

How can this be done? 

JIRA timeline.png

 

1 answer

0 votes
Magdalena Zhisheva
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 4, 2024

Hi @SDOB , 

I would like to suggest you to do the following:

1. Set your source to the scrum board related

2. Add the Sprint to your fields 

3. Add the due date and start date fields as well

4. Set the view to weeks

 

Then when you hover over to the timeline, it shows you the time based on the assigned sprint.

Screenshot 2024-07-04 at 17.40.41.png

Hope it works for you!

 

 

 