I mean some subtasks in different tasks
If you can find all the concerned issues with some criteria, you can do a bulk change and use operation Edit.
Then change assignee field
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I used:
project=<project> and type=Sub-task and parent=<parent's key>
From there, bulk update as noted above.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Do you mean all subtask of one task ? Or all subtask of the project ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.