When any user opens the Gantt it displays the default columns fields (assignee, units, priority, start, finish, duration, etc.). However, I changed the column fields to align to the fields that are applicable for our Gantt. How can I change the default view to reflect my new configuration, so it applies to any user who views the Gantt?
Hello Maggie 👋 welcome to the community!
Thank you for posting - Raphael from WBS Gantt-Chart support team here.
You can change your default column view in Top bar navigation Jira > Cog icon ⚙️ (left side of your avatar) > Apps > in WBS Gantt-chart menu, click Gantt Scheme > Configure > Columns
In this menu you can configure your default columns to the users, after editing it will only work for new Gantt created from now on. To change the current Gantt, you can access by you Gantt-Chart > top-right corner Cog icon ⚙️ (below your avatar) > Gantt configuration > on the tab navigation click Columns > edit your current columns. If you want to give the user permission to edit those fields, you can click on the Edit button on the right side, then flag Edit and finally click Update
Just as a kind reminder, when adding the columns to the users (either in Scheme or in WBS configuration), the columns will be located on the far right of the columns, after the default columns. These default columns are fixed to all Gantt-Charts.
Hope this helps to clarify your question. Please let us know if we can assist you with anything else!