Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to close issues in previous sprint

David McCarthy
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 21, 2018

We have a number of issues that were addressed in a previous sprint, but the sprint was closed without moving them to the done column, so they are showing up in our new sprint. They've been moved to done, but this is not correct ( as they are not completed in this sprint, but in our previous one ).

We want to be able to go back and mark these tasks as completed in the previous sprint, but I do not see how to do this.

Can you please advise how I can do this?

1 answer

0 votes
MoroSystems Support
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 21, 2018

Hello David,


have you tried just edit issues and delete value from Sprint field? Then only previous sprint should be stated in the Sprint field.

Cheers,
Milos

David McCarthy
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 21, 2018

Hi Milos, 

I believe this would take the issue out of our current sprint, but looking at the previous sprint report, all of these issues will still show up as incomplete.

If possible, we want to be able to have these issues be completed in the previous sprint.

Thanks,

David

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events