How to configure the "Resolved" or "Fixed" with "Remaining estimate" values

Doron Raiman February 25, 2012

Hi,

I'm looking to configure the following logic:

If a user is resolving an issue (regardless of the resolutions type) I want to indicate that the work on this issue was completed, which means the "remaining estimate" is zero.

Can anyone guide me where I can perform this change?

Thanks,

Doron.

2 answers

1 vote
Renjith Pillai
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 25, 2012

A post condition for the workflow to set the Remaining Estimate to zero should help you to achieve this.

Doron Raiman February 25, 2012

Thanks Renjith for your answer.
I'm not sure I understand what your'e asking me to do.
Sorry...

Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 25, 2012
Doron Raiman February 26, 2012

Great Renjith,
I'll try that and update you.

Thanks a lot.

0 votes
Gebsun
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 19, 2015

Log Work Utilities add-on allows to clear remaining estimate on issue close/resolve without a need to modify workflow: https://marketplace.atlassian.com/plugins/com.gebsun.plugins.jira.log-work-utilities/server/overview