Hi,
I'm looking to configure the following logic:
If a user is resolving an issue (regardless of the resolutions type) I want to indicate that the work on this issue was completed, which means the "remaining estimate" is zero.
Can anyone guide me where I can perform this change?
Thanks,
Doron.
A post condition for the workflow to set the Remaining Estimate to zero should help you to achieve this.
Thanks Renjith for your answer.
I'm not sure I understand what your'e asking me to do.
Sorry...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Log Work Utilities add-on allows to clear remaining estimate on issue close/resolve without a need to modify workflow: https://marketplace.atlassian.com/plugins/com.gebsun.plugins.jira.log-work-utilities/server/overview
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.