I have a main Epic E1 which has linked Epics E2, E3, etc. Each of the linked epics E2, E3, etc. help in fulfilling the main Epic E1. Each linked epic has its own Tasks.
It was recently decided to abandon this structure and keep only the main Epic E1, and convert all linked Epics E2, E3.. into Tasks under E1, and all previous Tasks into subtasks of the converted epics.
Current: EPIC has Epics has Tasks
Proposed: EPIC has Tasks has subtasks
Is there a way to easily convert Epics with Tasks into Task with subtasks?
Hi @Tushar Mathur ,
this is doable with some manual effort.
You can easily change the issue type from the UI if they are sharing the same workflow, if they have different workflows you can use the Move.
Anyway, I would use the following approach:
I hope this helps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Tushar Mathur - You can export the issues in CSV with Key, Summary and Issue Type and then import it after updating the Issue Type column.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.