We have a project in Jira named"OnlineBank". In this project, we have created 2 fields, Actual sprint and Planned sprint.
Now I need a gadget in dashboard that compares Actual Sprint and Planned Sprint.
Suggest me a method to do this
Hi @saranya22,
Welcome to this community :)
You can, for example, create a new filter like: "Actual sprint" is not empty and "Planned sprint is not empty" and save it.
After that you can add a new dashboard gadget of type: "Filter Results", select the filter just created and show this two fields in the columns.
I hope this help.
Cheers,
Adrián.
HI @saranya22
Use the Two Dimensional Filter Statistics Gadget add-on and mark the Custom Fields on the YAxis or XAxis fields. By this method, you can define if an issue is on an Actual Sprint Planned Spprint by using these values
Cheers,
Jason
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.