How to do critical path analysis in JIRA ?

Manoj Dadhich
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 2, 2022

I would like to identify the task falling in critical path based on the time lines of the stories.

Please help with the step.

3 answers

1 accepted

2 votes
Answer accepted
Kristján Geir Mathiesen
Community Champion
December 2, 2022

Hi @Manoj Dadhich and welcome to the Community!

One way to do this, using just Jira out-of-the-box, is to flag those issues that are on the critical path. Then you can either or both:

a) find them with a JQL search like:  Flagged = Impediment 

b) on a Kanban or Scrum board, create a quick filter (Flagged = Impediment) and thereby see them all by using the quick filter.

HTH,
KGM 

1 vote
Sidan Gao June 5, 2023

Hi Kristján, I have same request coming up and your answer is very helpful. Just want to check by "is to flag those issues that are on the critical path", are you saying we need to manually flag the issues on the critical path? Or is there a way to setup in Jira to flag them automatically?

Thanks!!

dstevens
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 10, 2024

If I could find the Critical Path tasks... I wouldn't need to flag them manually.  How to find the critical path tasks?

Like # people like this
0 votes
Mariano Tallarico _Appricity_
Contributor
September 20, 2024

Hello everyone. I don't know if this is related to BigPicture, or if it is something native to Jira. In my case, we use BigPicture, and we have the same problem. We have the need to work, dynamically, with those tickets that (depending on the context of the project) belong to the Critical path.

I was recently in contact with Big Picture Support, asking them about it, and they told me that at the moment, in BigPicture, "the critical path is just a visual highlight of the tasks in Gantt and there is no way to identify and filter the tasks that are on a critical path according to Jira fields/tags."

That said, they have a pending ticket to cover this functionality: https://appfire.atlassian.net/browse/BP-6068 (use incognito mode to access it).

I hope I have been able to contribute to the cause, if this is still pending. In my case, I will continue looking for alternatives until they make the improvement.