Hello,
I am following this steps to end a sprint.
http://confluence.atlassian.com/display/GH/Ending+a+Sprint
However, I get message, "Sprint cannot be completed as there are incomplete subtasks on the following issues: XXX" even though all subtasks are done.
My team is using our own workflow (not JIRA default) for technical subtasks, and it is all marked as "Done" (please refer screenshot).
Why I cannot end sprint? What am I missing here?
Thank you!
Miki
Make sure in your custom workflow, the transition to your Done status actually resolves the issue. This is usually handled by setting up a post function for the transition that fires an Issue Resolved event. See workflow documentation for more detail: http://confluence.atlassian.com/display/JIRA/Configuring+Workflow#ConfiguringWorkflow-workflowresolutions
Hi Danielle,
Thank you for your answer!! I knew I was missing something in my custom workflow, but I could not figure. I was able to end a sprint properly.
Miki
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Miki, you are most welcome. Glad it helped.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.