Hi,
We are just starting to evaluate JIRA Portfolio for planning our roadmap and I am not really sure how outsourcing teams should be handled. For example lets say we have a project that has an estimate of 500 hours out of which 400 hours will be developed by an outsourced team which does not have access to JIRA.
Prior to portfolio we would only create the 100 hour task in JIRA but now that we want to have the roadmap in portfolio having the outsourcing time should be considered.
Has anyone else run into this scenario? What is the recommended approach?
Thanks for any insight!
Tudor
Hello,
You can create a new team, and assign "virtual users" that would be taken into account as "outsourced team members".
More information here.
Cheers,
Maria
Portfolio Tech Writer
Thank you Maria, I completely overlooked the virtual users option!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.