HI
Once an issue on the kanban board is in final status - I would like to see it on the finished items column for a period of time and then to have it removed otherwise the column is getting packed.
How do I do that?
Thanks,
Hi @Rony Len what we are doing is indeed like Maksim suggested which is
YOUR FILTER AND (status != closed OR status changed to closed after -7d )
In Jira Server, there is a built-in option to do this, without even changing the filter.
It seems to me the most correct decision will be based on a resolved date:
resolved >= -1w
But at the same time, nothing prevents to list all the final statuses:
status changed to closed after -7d OR status changed to Cancelled after -7d
Depends on your workflow
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I cannot seem to find custom statuses to use in the argument 'status changed to...'
if I use ("custom status x") it is supposed to work?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rony
You need to use Kanban board sub-filter. For example:
resolved >= -1w
https://confluence.atlassian.com/jirasoftwarecloud/configuring-filters-764477988.html