How to make roadmap works for classic project?

David Leal August 26, 2020

In Jira Cloud I have Roadmap feature as Beta. I am trying to use it, but I am not able to figure out how. Per the documentation: Set up the roadmap it specifies that in order to make it works the Start date and Due date need to be configured the field layout for epics to set these dates, the link provides a generic reference about field configuration, but not about these specific ones.

This is how I indicate in the Default Issue Screen to visualize both Start Date and Due Date:

dueDate_Jira.JPGin the Default Issue Screen, then I can see Start Date, but not Due Date, I can add Due Date in the card layout in the board, so the field is there, but in the issue detail view the information doesn't show:dueDateEpicDetail_Jira.JPG

so because I am no able to set up both values I can not move the bars in the roadmap, and it shows:

roadMapNoStartDueDate.png

No Due Date, No Start Date in the roadmap, so I can not move the epic in the time-schedule.

I was trying to find some video or documentation about how to set up the RoadMap so I can make it works, but I was not able to find something specific.

It is a very useful tool once I figure out how to use it.

Thanks for any help,

David

2 answers

0 votes
David Leal August 27, 2020

Trying to find some workaround to this problem I found the root cause of this problem.

I was trying to create a new epic issue, then to add DUE DATE field, i.e. Create->Configure Fields->Where is my Field?-> Add DUE DATE in the search box. Jira is able to find it, but it shows the following message about it:

 

image.png

image.png

so the issue may be related with my user or Permission. I am the Jira Admin, but I did not add myself as a member of the project, so I did it as Administrators and the problem persists. Then I realized that maybe the issue is the Permissions and for Schedule Issues permission only the following roles have it:

  • Project Role (atlassian-addons-project-access)
  • Project Role (Scrum Master)

so Administrators don't have such permission, then I changed my role to Scrum Master and finally, I was able to drag and drop the epic in the RoadMap:

image.png

It is weird to me that even a Product Owner cannot change the road map.

What I don't really understand is how come after 18 years in the market this tool is so little user friendly

Sramanth Pandeti
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 28, 2020

@David Leal I am glad you found the solution for this. :) and Yes, I forgot to mention this in my previous response. For setting up the Due date field, you need to have schedule issues permission. I know with lot of permissions in place , it can be frustrating at times. 

0 votes
Sramanth Pandeti
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 27, 2020

@David Leal It might be possible that there is another DUE date field specific to the roadmaps. Can you check with your Jira admins and see if you can add the field to your project screen scheme and then verify it? 

David Leal August 27, 2020

I am afraid that this is not the root cause of my problem. I am one of the Jira Admin.

This is my Field Configuration:

 

image.png

The DUE DATE field is there and I see my project screen assigned:

image.png

In my Issue Type Scheme I am using he project default Scren Scheme and the Default Field Configuration:

image.pngRegards,

David

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events