My team works in 2-week sprints from Wed - Tues. I want a rule to run daily at 9 AM on the second week of the sprint (the second Wed - Tues). I cannot figure out a way to express this in CRON. I saw https://community.atlassian.com/t5/Jira-questions/How-can-I-schedule-a-rule-to-run-every-2-weeks-on-a-particular/qaq-p/655520, but I could not get it to work since Wed-Fri will run opposite weeks than Mon-Tues. Do I need to split this into 2 rules? And how would I add the condition so Wed-Fri. runs on odd weeks and Mon-Tues on even?
Hi Katherine
yes. I think 2 rules will do the trick. And you kick of the rules at the time when it is in sync with the 2 week rhythm of your sprint. I.e. you may have to wait a week to kick it off.
Would be interesting to hear back from you how solved it.