Hi there, 

I am looking to develop a RAIDD dashboard for my team. We are paying the standard subscription and have two active boards that were migrated to us from an external consultant we contracted. How do I: 

1. Create a backlog using the existing board/s with all new risks, issues, decisions and parking lot items. 

2. Be able to link risks and issues with each other.

3. See the backlog of risks, issues, decisions and parking lot items visible (pie chart view). 

I have already created the dashboard but finding it difficult on next steps around creating individual risks, issues, decisions and parking lot items that can be visible on the dashboard. 

I would appreciate a step by step manual on how to successfully perform this task. 

Thank you,

 

2 answers

1 accepted

1 vote
Answer accepted
Danut M _StonikByte_
Atlassian Partner
November 5, 2024

Hi @Beejal.Batavia,

You could define an issue type in Jira (with the appropriate fields) for each of them: Risk, Assumption, Issue, Decision, Dependency, etc 

Once you have these issue types defined, you can add the items with the appropriate type (risks, assumptions, issues, etc).

Then, linking risk to issues can simply be done by using the Link button from each item.

And you can add all kind of statistics displayed in your dashboards by using the Jira's native gadgets like Pie Chart gadget, Two Dimentional Filter Statistics gadget or Issue Statistics gadget.

Danut.   

Beejal.Batavia
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 24, 2024

Hi Danut, 

Thank you for providing these steps, I have managed to successfully build my platform. 

Much appreciated, 

Beejal 

1 vote
Monika Isak
Contributor
November 5, 2024

Hi @Beejal.Batavia

We can help you build a spreadsheet-looking table view that you can divide your Risks-Assumptions-Decisions-Dependencies into separate sheets and apply also a Risk Model for your risk assessment. Unlike the Boards, you can work with the content directly in the Table view.

We would love to show the capabilities of the Risk Manager Plus app. You are most welcome to book a suitable date and time to have this discussion.

Greetings!

Monika

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events