Hi everybody!
I want to see the % Done tasks in Story, into Backlog view. I'm getting crazy to find something to get that value.
As you can see in the img, that value exists, but i want to see it into general backlog view.
This is possible?
Thanks!
Hi @Marc R
In the backlog view, Sub-tasks are normally not displayed and we can not show the % of done for subtasks in backlog view too.
It is not possible.
Wow! I'm surprised!
For me this value is very important, there is some way to see something similar? I want to know the % of completed Story, into backlog view.
Thanks @Monika Rani for answer!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I'm afraid Atlassian are quite Agile purists. Sub-tasks are irrelevant to the backlog. A story is either done or it is not. 0% done, 1% done, 99% done - all mean "not done".
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
that's surprise me, because Jira it's famous for its flexibility. And it's hard to believe why it's not possible to show this value into backlog view. For me it's a useful value.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.