I have a board where its showing old sprint tickets in New sprint , Old sprint tickets are in DONE status, i am looking for a solution where i dont see old tickets anymore.
Hi @anil musunuru ,
As @Matt Doar suggested ,
1.does the old sprint issues are having resolution first.
2. If you have some sub-tasks pending (Status Not Done) while closing a sprint. those will be sent back to backlog or upcoming sprint.
3. If any statuses are not tagged under board columns, stories will be sent back to backlog / Next sprint.
Check these above cases.