I need to see who did work on each task in previous sprints and how much time they charged. But I only can see on one by one base, and can't see the whole sprint with all the contributors time and list of tasks the worked on.
I would appreciate it if you can assist me in the right report.
Hi @ghodratb
the easiest way of achieving that would be using one of the many worklogs reporting apps from the marketplace. I am sure you can find a perfect app for you there:
Thank you. This did work. Great suggestion.