How to track how many tickets closed by devs

Eugene January 18, 2019

Hi, can you please advise how company can track how many tickets done by dev during a sprint.

 

Our flow is - Open ->  In Progress -> Ready for QA -> Closed

 

Dev assign ticket to QA and QA close all tickets.

 

How in this case company can see how many tickets was closed/fixed by dev, if at the end all tickets with QA

1 answer

0 votes
Ismael Jimoh
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 18, 2019

Hi @Eugene Semenov

Let us assume your sprint runs weekly or bi-weekly. If so I will do the following 

  1. Create a date custom field that is filled when the issue is being transitioned to Ready for QA via post function.
  2. Now using JQL you can filter for all issues whose date is between the start and end date of the sprint.

This is the process that comes to me offhand.

Eugene January 19, 2019

Thank you Ismael