I created an excel project schedule (simple gantt chart)
I uploaded it on Sharepoint
I want to upload the same chart on Jira and synchronize it with the excel on Sharepoint. So whenever I make any changes in the excel the table in Jira page will also update itself.
You won't be able to do this @Ayxan Mamedoff - the line items need to match up to tickets in Jira somehow and the whole exercise will end up pretty horrendous.
Best option is to look at a cost effective Gantt Chart option in Jira which you can then extract to excel if absolutely needed (any particular reason you can't just keep things in Jira?).
BigGantt from Software Plant is probably the most popular option: https://softwareplant.com/biggantt/
Also worth exploring: https://almworks.com/gantt/overview.html
Hi @Ayxan Mamedoff
@Kit Friend mentioned about BigGantt. Let me present this tool ina nutshell. The plugin not only visualizes Jira data but also supports project planning, managing, and tracking. Below you can find a brief description of the main functionalities.
BigGantt is bi-directional synchronized with Jira.
Moreover, with BigTemplate App you can unlock import features.
In case of further questions, just let me know in this thread.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.