Without due date from Dec1- NOW; without work assigned for upcoming 2 weeks and onward; longest planned due date/longest task; no of tasks on hand
implimentation
Tasks and sub-tasks without a due date;
Members without work assigned for upcoming 2 weeks and onward;
longest planned due date/longest task;
Number of tasks on hand (to do, open);
From 2019-12-01 to NOW;
can you please help on this .
Thank you.
I think this will get you started.
XXX is your project. There are several ways to look at this, and you can use filters and boards pretty effectively to get what you need. If it's something you track routinely, I'd look at building dashboards.
Tasks and sub-tasks without a due date;
1a. project = XXX AND type in (Task, Sub-task) and duedate is EMPTYMembers without work assigned for upcoming 2 weeks and onward;
2a. Pretty challenging - Jira queries issues,not people You might be able to querylongest planned due date/longest task;
3a. project = XXXAND duedate is not EMPTY ORDER BY due DESCNumber of tasks on hand (to do, open);
4a. I would do this via a kanban board, but you can query project = XXX and status in ("To Do", open)From 2019-12-01 to NOW;
5a. project = XXX AND createddate >= '2019-12-01' and duedate is EMPTYJust straight JQL or are you working on a dashboard?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.