Our teams are having a bit of issue staying synced on separate projects, for example, there are 3 silos, front end, back end, and business, then we have various projects that we rely on each other upon. I want a visualization that shows all the projects, and for each project where each team is at on the tasks for the project. For example, it should be really easy to see if the business team is finished their task on a certain project so the backend team can then start their task for it, where upon the front end team can see where the other two teams are at.
This should be a top level view for all the projects and for all the teams.
I have tried something similar in our Jira. I have a board that pulls all the issues in different projects based on a label. So, any issue/task that you want to be seen on a global board, just add a label and ensure those projects have the issue pulled into a sprint. Hope this helps.