I'm looking to include the Due Date in the card layout, but I'm having trouble figuring out the best location for it. I need guidance on where to position it within the design to ensure it’s both visible and appropriately placed without affecting the overall layout.And iam using Team Managed Project
Hi @Ramya
Welcome to Atlassian Community!
It is currently only possible to change the card layout in company-managed projects, but not in team-managed projects. There is a feature request you can vote and watch to receive updates on its progress.
Thanks!
Hello @Ramya,
In Team-Managed Jira projects, you cannot customize the exact placement of fields on the card layout. However, the built-in "Due date" field will automatically display on the card if it contains a value. Customization options for card layouts are limited compared to Company-Managed projects.
Ensure you are using the built-in "Due date" system field, not a custom field with a similar name. Only the system field triggers automatic display on cards
I found a similar question here - https://community.atlassian.com/forums/Jira-questions/Add-due-date-to-card-view-in-Software-Project/qaq-p/2584511 and
There is also a feature request to address this - https://jira.atlassian.com/browse/JRACLOUD-85694