Is it possible to generate a burndown chart based on points being spent each day instead of tracking time in hours?
I'm not sure what do you mean by "Points being spent each day" but there are 2 configurations for the JIRA Burndown chart for Time Tracking.
One is the by "Remaining Estimate and Time Spent" and the other one is by "Issues will burn down their Story Points value upon completion"
Configure your board then open the "Estimation" tab to see this configs.
It looks like I want to use "Remaining Estimate and Time Spent" since I want it updated daily instead of upon completion of the story. But I'd like to record the "Remaining Estimate" as story points, not hours or minutes.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.