I would like to use release and version reports with remaining estimate instead of story points.

Kathy Adams December 4, 2018

 We use original and remaining estimate.   Is there a setting on the release and version reports to work with  one of these rather than story points?

1 answer

1 accepted

1 vote
Answer accepted
Morgan Folsom
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 4, 2018

Hi Kathy, 

The Version Report will use the Estimation that is set on the Board. 

For each board you can select an Estimation statistic - whether it is Story Points, Original Estimate, a custom number field, etc. That estimation is what is used for reporting. What you cannot do however, is use story points on your board, but have these reports show Original Estimate. 

To view/change the estimation statistic for a board, you can go into Board Configuration -> Estimation.

 

Morgan