I am not able to browse through the tasks in a completed sprint. Once I complete a sprint, i wont be able to go back and see the tasks.
Welcome to the community
As @Y Dang_Candylio mentions the correct options, it could be that you have to look at the following.
Team managed projects have by default, reporting disabled. Go into to project settings and via the Features option you can enable the reports.
Also their is no sprint report in team managed projects, only burn up and burn down reports
You can see completed sprints by going to the Reports section and looking at the Sprint Report (or Sprint Burndown Report, if you are using a Team Managed project. Select the sprint you want to view. If you need to reopen the sprint you can do that by clicking on the '...' button on the right above the chart.
In Team-managed project, only one sprint can be active at a time, so if you are using that type of project you will only be able to reopen a sprint if no other sprint is active.
In Company-managed project, you may have multiple sprints open if the global setting to allow Parallel Sprints has been enabled.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.