If I update the Orginal estimate the estimations in Time Tracking is not updated

ioana_codruta_crizboi
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 17, 2019

Hi,

I updated the Orginal estimate field and the Time Tracking estimations is not updated. Now I have 2d h in Orginal estimate and 1d 4h in Time Tracking. That's messing with my Reports. How can this be fixed?

 

Capture.JPG

Thanks,

C

2 answers

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 18, 2019

Because it is supposed to record the estimate you made first, and then track changes to the estimate as updates, without losing what you originally said.

It's not messing with your reports, it's telling you what was changed.

0 votes
Derek Adkins
Contributor
May 24, 2021

I agree. If no time is logged yet, then the time remaining should always match the original estimate value.  

I think there might be a case to keep it the way it is, after someone has logged time... but not prior.