Import from CSV - No Issues with import BUT Original Estimate hours not showing on individual story

Lauren
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 31, 2018

When I import stories from a CSV file and click "validate" it comes back with no issues. I then click "begin import" which works... however when I click on individual tickets the "Due Date" appears to have the incorrect date (wrong year), and the "Original Estimate" values are missing (defaulting to 0h in ticket).

How can I fix this so that it reflects the correct date and estimate in my tickets?

 

Please see screenshots below for:

1) CSV file values (see Original Estimate & Due date)

CSV values.JPG

2) Mapped Fields

Map Fields.JPG

3) Mapped Values

Map Values.JPG

4) Fields in ticket with incorrect date and missing hours

Fields in Ticket Created - Incorrect + Missing.JPG

 

1 answer

0 votes
Thomas Deiler
Community Champion
January 31, 2018

Dear @Lauren,

  • The date is not correctly imported due to date string format. Have a look at that article.
  • The estimate is not in milliseconds. See this article.

So long

Thomas

Thomas Deiler
Community Champion
February 2, 2018

Dear @Lauren,

you didn't come back - have you solved your problem meanwhile?

So long

Thomas