Zara May 5, 2020

In my Dashboard, I add the Sprint Burndown. 

The sprint burndown is showing hours (Remaining Time estimate), not story points.

How can I change this to story points?

Note- The board itself has estimation =story points. 

1 answer

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 26, 2020

Hi @Zara 

That gadget is supposed to use the estimate for the board.  Looking at some other community posts, there could be some caching of settings.  Have you tried to remove the gadget, confirm your board settings, and then re-add the gadget?

 