In Greehopper's "Work" board, user histories with no sub-tasks are grouped under the swimlane "Other Issues", thus losing its priority.
Example:
Up to this poing, everything's fine. The problem comes here:
Is there anyone suffering this problem too? Are we doing something wrong?
Hi Fernando,
You could base your Swimlanes on queries and add the swimlane with the following JQL to the top (issuetype=Bug) that should place your bugs always in a seperate swimlane on top.
If you do this you will loose the Swimlanes based on stories, so this might not be what you want.
Best regards,
Peter
Wow, I didn't know I could do that.
You are right, I need my story-based swimlanes, but now it's clear to me that I need to investigate further what kind of things can we do with JQL. Maybe there's something there we could use for this problem.
Thanks a lot.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
We have the same exact problem. We only create sub-tasks if the bug or story is estimated to take more than 4 hours to get to "Done." I would like our task board ("Work" rapid board view) to appear as folllows, preserving the product backlog order defined on the "Plan" view:
Bug (no subtasks)
Bug
- Subtask
- Subtask
Story (no subtasks)
Story
- Subtask
- Subtask
- Subtask
Story (no subtasks)
Without this capability, there's no way for the team to work in the product owner-specified priority order unless we create a "fake" subtask for every bug or story which, as Fernando points out, is a waste of time and provides no value...it's just a work-around.
Please help!
Thanks,
Dave
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
That's exactly my problem, Dave. Thanks for the description, it's really easy to understand in the way you put it.
In the meantime, I'm trying to find plugins to make easier to create sub-tasks.
https://marketplace.atlassian.com/plugins/com.atlassian.jira.copy-to-subtask-plugin
If someone finds a plugin to create automatically sub-tasks, I would love to try it.
Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Try: Configure | Swimlanes --> Base Swimlanes on "No Swimlanes"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your suggestion, Tom.
I have tried and it solves a part of the puzzle, but at the cost of losing the relative priority between columns that provide story-based swimlanes, which I'd like to maintain.
Good suggestion, though, and gave me an idea about some other thing I needed, so thanks indeed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.