Is there a way to setup Dependencies between stories in Jira Agile? So that you can tell if Story A has to be done before Story B.
In the Agile methodology, a Story should follow the INVEST mnemonic and should aim to be as independant as possible. Now, if that is impossible, the order of the product backlog should give you the dependencies you need. If A has to be done before B, then A should be higher than B. Finally, if you really looking for a way to mark that dependency, you could use the JIRA issue link function.
But ordering stories in the backlog won't help you manage dependencies if you have many developers working independently.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.