Given the new feature in 2.6 to view a whole portfolio of plans, Can or does portfolio support dependencies across plans now? This is critical given the fact that there is a 5000 issue limit in a single plan.
To add to this, I set up a Program (Space Program)that contained two Plans (Inner Planets and Outer Planets), each connected to two boards (see screenshot, Mercury and Venus, Jupiter and Saturn). Indeed, there's no way to set or view Dependencies in a Program. This includes the Dependency report.
It's also worth noting: you can only drill down to the Epic level in a Program, so the dependencies would have to be at the Epic level or higher in your hierarchy. If you were expecting/hoping to see Story-level dependencies (just like in the individual Plans), you would not be able to see that or set those in a Program. Something to consider when voting for the issue above.
-Jason Golden
Denver AUG Leader
Hi Wally,
I checked on this and if you're talking about the dependency report, it only works within a plan. At this time I would vote on JPOSERVER-1218 and add your use case to the comments.
This will notify you when a change is made to the ticket including updates and a fix version.
Cheers,
Branden
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.