I'm using portfolio for our Roadmap which meant that the scope I'm playing with covers multiples years.
I would like to know if this is possible to have the team velocity increase over time ... let say, 10% each year.
Hi @Nicolas Gendron,
This is currently not supported directly but as a workaround if you are using time planing I'd suggest having a look at exceptions which allow to define a team member weekly capacity over a specific period of time.
Also I've created a feature suggestion for Portfolio for Jira server here: JPOSERVER-2044
Cheers,
Thomas.