Hi Team,
I'm working with Portfolio for Jira right now (server). The issue I face is the following:
1) I have a user story with estimate = 10 hours
2) I want to assign user1 and user2 to work on this user story
3) I need to allocate user1 to work on this issue 2h/day, then user2 3h/day
Are there any workarounds at Portfolio for Jira?
Jira Software version: 7.7.1
Portfolio for Jira version: 2.12.1
Thanks in advance!
Hi Kyrylo,
In order to assign multiple users to a single story, you will need to assign the it to a team. Then, you will be able to assign members of that team to this story.
To read more about team member assignments, please take a look at our documentation; https://confluence.atlassian.com/jiraportfolioserver/releases-teams-and-member-assignments-715262710.html
If you need help with configuring team settings, please take a look at https://confluence.atlassian.com/jiraportfoliocloud/configuring-team-settings-828785279.html Here, you will be able to configure weekly team member working hours.
Please do not hesitate to reach out if you have any further questions.
Regards,
The team at Portfolio for Jira.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.