Is it possible to sync the order of the sub-tasks in the board and in the (parent) ticket views

Bruno Pontes
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 29, 2021

Hi Everyone!

 

My teams usually organise the order of their work by going to a parent ticket, creating subtasks and ordering them so that everyone knows that what should they work on next.

 

The issue is that if the team sets the order in the parent ticket, that same order will not (necessarily) be reflected in the board view (grouped by Subtasks).

 

Is that a way to synchronise it? (Without having to do it manually)

 

Thank you in advance

1 answer

1 accepted

0 votes
Answer accepted
Guilhem Dupuy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 30, 2021

Hi @Bruno Pontes ,

As far as I know, there is no way to synchronise these 2 views to avoid reordering them manually in the Board view;

However, you could build a workaround like playing with the priorities of the subtask, and ordering your Board view by priority, but you will then loose the possibility to reorder manually the tasks and subtasks from your board.

 

Let me know if it helps,

Guilhem