Hi,
By default presented with Issue Types - EPIC - BUG - STORY - TASK.
If adding a new issue type for example INITIATIVE, how do I make this the top level issue type.
ie. INITIATIVES are made up of EPICS... EPICS are made up of STORYs... STORYs made up of TASKs.
Hi Simon!
If I understand you correctly, you want to set a custom issue type called "Initiative" as the highest level of issue in your instance.
To do this, you have to go here and add it:
Hit the "Create level", add the "initiative" issue type and arrange them at your own will.
Remember to click "Save Changes".
Also: Changes to the hierarchy configuration will only apply to plans in Advanced Roadmaps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I'm trying to do the same thing, and create a 5 level hierarchy with a few new types, and t's letting me create the types, but it doesn't seem to be allowing me to establish the hierarchy I want? Thoughts? I want Project --> Stage --> Epic --> Story --> Task --> Sub Task, with Milestone and Deliverable as additional Sub Tasks...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.