Created a task with several subtasks. One of them was put on resolved and a green checkmark appeared on the main task site (correct).
But: after changing the status back to new, the check mark still remains.
Does your workflow blank out the "resolution" field when you use "reopen"?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Exactly what I said. Look at your workflow. Does it clear the "resolution" field when you use the "reopen" transition from "resolved" to "new"? The tick-flag comes from that field.
For more info on workflows and a better explanation that I can give, see https://confluence.atlassian.com/display/JIRA/Configuring+Workflow
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
When you change the Status, you have the possibility to also change the resolution. If you don't change the resolution it seems to change automatically.
But now I see: When you change to Status "Back To To Do", then you have the possibility to have the resolution "Done". That does not match,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
On a re-open transition, you should make sure it uses a screen (or doesn't have one at all) that does not include resolution, and clear it with a post-function.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.