Hi,
I have a 'company managed' board with three columns (to do, in progress and done). When I close a sprint (e.g. sprint 1) and start a new sprint (e.g. sprint 2) the items in the furthest right column (i.e. done) from the first sprint are appearing in the second sprint, leaving the history of sprint 1 empty.
I have reviewed other Q&A and they all reference the issue being caused by either a team managed board or done not being the furthest right column.
Could anyone advise me on what else I could try?
Thanks
Adrian
Hi Adrian,
you could also check whether the Resolution of the issues is set correctly when they are in Done.