We have a planning Kanban board outside of the sprint board that isn't displaying any of the backlog
Statuses are mapped in the columns, and the filter query shows the issues.
EDIT: I found a solution! In my case, the problem was "Kanban board sub-filter". Usually this field should be empty, but for some reasons I had a JQL expression there.
To edit this field, access: Project > Kanban board > Board settings (tree dots on top right) > General > Kanban board sub-filter.
In my case, when I cleaned that field, everything worked again.
--------------------
Hello there! I have the same problem =/
Were you able to find a solution?
Thanks!
In your filter screen I can see "Save as" option.
If you're not the owner of the filter you won't be able to modify it, try to create a new filter with the issues you need need for your Kanban Planning board and then update the filter in General Configuration of my board.
Also I can see that you are filtering ToDo status but Todo is not mapped in your columns.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.