Hello all, I have a simple automation rule that should work like this:
IF an epic is created
THEN create
- task1
- task2
- task3
Now, I would like that this rule could also open a subtask of task1, but I only managed to open the subtask under the EPIC. Is there any way to achive this kind of automation?
Thanks!
Hi Giurgola,
Yes, you can achieve this using the branch rule / related issues feature after each task and for Type of related issues, select Most recently created issue and then create an action to create the subtask.
Hope this helps!
Best,
Bhanh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Diego,
Branching into related issues in this way only works until one level deep unfortunately. However, you could solve this by creating a new automation that triggers on the creation of task1.
Some pointers:
Hope you can get started with this?
Jeroen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.