JIRA Agile: Is it possible to have different sprint lengths for different projects?

LEM
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 8, 2013

Normally we have 2-week-sprints, but we'll have a special project with 1-week-sprints. Is it possible to change that for this project only?

If yes: how?

System:

  • JIRA: 5.2.6
  • JIRA Agile (Greenhopper): 6.2.5.1

3 answers

1 accepted

0 votes
Answer accepted
Peter Van de Voorde
Community Champion
December 8, 2013

Hi Werner,

Currently that's not possible, look here for change requests about this issue:

https://jira.atlassian.com/browse/GHS-7809

https://jira.atlassian.com/browse/GHS-6858

So I'm afraid you'll have to do it manually.

Best regards,

Peter

LEM
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 8, 2013

Thanks Peter!

I voted for both issues, so maybe I'll be lucky.

0 votes
LEM
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 8, 2013

Hi Peter,

yeah, I know that :-)

I guess my first entry was a bit misleading...

Its about the following screen that comes up when starting a sprint. I'd like to get a default of one week for a particular project.

0 votes
Peter Van de Voorde
Community Champion
December 8, 2013

Hi Werner,

You can indicate a start and end date when you start a Sprint.

It's perfectly possible to change this.

So short answer : Yes :)

Best regards,

Peter