As you can see from the image above, I have an epic called "Setting up office environment" , the duration of this task, as you can see in the yellow box, is "3 working days".
The epic contains 3 issues:
The point is SW-33 and SW-4 done simultaneity by me and my college together in the same days.
Images are as below, from left: SW-33, SW-4, SW-14
Screen Shot 2014-11-18 at 19.53.53.png
_______________________________________________________________
Screen Shot 2014-11-18 at 19.54.09.png
________________________________________________________________
Screen Shot 2014-11-18 at 19.54.26.png
The problem is that the Gantt-chart plugin marked the epic as "Over-capacity: planned 166% allocated work, current need: 0%", which is wrong . Actually I think its calculated as followings:
((∑Original estimates)/(Duration))*100
In this case
((0.33+2.33+2.33)/(3))*100=166%
Which is wrong, because the task is not over capacity and the epic distributed between 2 people and it can be done in 3 days. Because the two 2.33s in the above calculation were done simulantely , I think it must be calculated as this (it can be rounded or calculated other ways)
((0.33+2.33)/(3))*100
What's wrong ? Is it really the problem ?
Fixed within Gantt-Chart pre-v3.1.6, available for download from my server at http://www.polscheit.de/plugins/jira/gantt-chart/gantt-3.1.6-JIRA6.jar: download JAR-file and install it via "upload" button on JIRA's page "manage add-ons" as system admin.
Kind regards,
Frank
Thanks dear @Frank Polscheit , but it didn't solved the problem, the over-capacity errror still there. What do you suggest ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Michel,
you're correct: there is no distinction between different assignees, currently. I have placed that topic to be fixed within coming version 3.1.6. As epics are kind of containers of issues possibly belonging to different team members, a single indicator of over-capacity does not really make sense within this context: but per assignee, they are useful.
Kind regards,
Frank
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear @Frank Polscheit,
So many thanks for great support and time you spent on this issue.
I've updated the module and now it shows Version: 3.1.6-JIRA6 in the Admin panel. But the problem still exists on the gantt chart. (It still shows over capacity for the epic)
I tried reindexing + log-out and log-in but no difference.
What do you suggest?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear @Frank Polscheit , I'll be glad if you can answer this question :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.